MAZDA TOYOTA MANUFACTURING US
The scope of work performed by Superior Electric at the new MTMUS facility was vast: We were the installing contractor for the entire sitewide 15KV distribution to all of the MTMUS buildings, along with all of the 3rd party on-site suppliers. Upwards of 80,000’ of MV cable was installed during this project. We were also the electrical contractor for the 1.5 million sq ft MTMUS General […]
GM DMAX BROOKEVILLE
This project was a 251,000 sq ft building built in 2020 to allow GM/DMAX to produce overflow parts for the Duramax Diesel engines they build jointly. The project included new primary service, (1) substation room with (4) power and lighting subs, (6) new 1600a bus feeds and complete 480v distribution systems, LED building lighting, sight lighting, […]
MERIDIAN MAGNESIUM BUILDING REMEDIATION
Summary: On May 2, 2018 Meridian Magnesium experienced a catastrophic fire and explosion. While no lives were lost, 2 employees were injured, and their manufacturing process was destroyed. Walbridge and Ford Motor Company marshaled a global team of experts to remedy the immediate situation and rebuild the facility to resume manufacturing. SEGLC’s expertise in many […]
GM ENTERPRISE DATA CENTER – WARREN TECHNICAL CENTER
Summary: This project was a building expansion at the GM Warren Tech Center consisting of (4) data halls, (5) chillers, (5) cooling towers, (4) redundant MV line-ups, (8) 2.5 megawatt UPS generators, and (4) 2 megawatt generators. Multiple voltages were used throughout the facility between the UPS and mechanical required loads. Project began as plans and specs, but […]